Oxford Street Winchester Street Intersection

What

Undertaking minor intersection improvements that include; kerb alterations, line marking, car parking definition and tactile paver installation.

Why

To improve pedestrian safety on this intersection.

Where

Intersection of Oxford and Winchester Streets, Lyttelton, Christchurch City

When

Work will start Mid January 2019 to Late February 2019.

Contact

The contractor is John Fillmore Contracting Ltd. Phone (03) 343 1057 Monday to Friday. Advise us if you have specific property access requirements e.g medical visits, home help, large vehicle deliveries, planned works.

  • Works will be undertaken on day shifts between 7am to 7pm (Monday to Saturday).
  • There will be some noise disturbance during the work. 
  • Programming of these works to an exact date is difficult as dry weather conditions are required for road surfacing and line marking operations to achieve a good result.
  • Street side parking may be temporarily unavailable throughout the works.
  • Temporary footpath closures / cordoned areas during works may be encountered.
  • Road shoulder and temporary lane closures will be required to under take the works safety.
  • Delays through this intersection can be expected.
  • The start and completion dates are subject to weather conditions, road corridor operations.