Hill Suburbs Watermains Renewal

What

Renewal of the Watermain in Governors Bay Road

Why

To replace the existing watermain which is at the end of it's economic life.

Where

Governors Bay Road from Number 1 to mariners Cove.

When

Work will start early December 2018 to mid February 2019.

Contact

The contractor is City Care Ltd. Phone 0272-480-337 between 8:00am to 5:00pm Monday to Friday. Advise us if you have specific property access requirements e.g medical visits, home help, large vehicle deliveries, planned works.

  • Owing to the number of services and the position of them, the new watermain needs to be placed in the middle of a traffic lane for part of its length. The road will be one way past the works to allow the pipeline to be laid.
  • It is expected that some rock will need to be excavated to lay the pipeline. Progress will be slow if a great amount of rock needs to be excavated.
  • Traffic management will be installed to keep both the workers and road users safe. Please be aware that a reduced speed limit will be in place going through the site.
  • Access to properties will be maintained using steel plates where required. On road parking will be limited during the works.
  • Please phone Grant Deeney, City Care's Contract Manager, phone 0272-480-337, should you have any questions or concerns.
  • There will be a water shut off when the new mains are connected over. You will receive a water shut off notice with a time when this is known.

Takiuru ki ā mātou ratonga
Log in to our services