Retaining Wall Repairs- Godley Quay

What

Repairs to the red stone retaining wall.

Why

To undertake repairs to the damaged sections of the wall.

Where

22 Godley Quay, Lyttelton.

When

Work will start 1 December 2018 to 20 December 2018.

Contact

The contractor is Hunter Civil Ltd. Phone 03 381 7094 between 8:00am and 5:00pm Monday to Friday. Advise us if you have specific property access requirements e.g medical visits, home help, large vehicle deliveries, planned works.

The works involve:

  • The removal and relocation of the top three layers of red stone blocks that have rotated towards the footpath.
  • The trimming and planting of the exposed bank.

The roadway will remain open to traffic during the works.

The works will take about 7 days to complete.

 