Quarryman's Trail Major Cycle Route

What

Carriageway resurfacing, new kerb and channels and new footpath

Why

We are developing a network of 13 Major Cycle Routes linking shopping centres, businesses, schools, parks and popular recreation destinations
Cycle routes are also a proven way to improve the health of the city, reduce congestion, build stronger local economies and reduce the cost of infrastructure. Bike-friendly cities consistently rank highly in quality of life surveys – cities where it’s easy to get around by bike are great places to live.
For more information about the Major Cycle Routes visit www.ccc.govt.nz/cycleways

Where

Sparks Road from Victors Road intersection to Te Hāpua Centre on Halswell Road

When

Mid November 2018 and will be completed in stages by July 2019
You will receive work notices from the contractors as they begin work in your street. These notices will provide information on what work is taking place, traffic impact, any access restrictions and contractor contact details

Contact

The contractor is Fulton Hogan Ltd. Phone 0800 275 342 between 7.30am - 5.30pm (Monday to Friday). Advise us if you have specific property access requirements e.g. medical visits, home help, large vehicle deliveries, planned works.

  • We will be installing two new sets of traffic signals at the Henderson Road/Sparks Road intersection and a mid-block crossing on Sparks Road at Milns Drain Reserve.  We will also be constructing 3,800m of off road cycleway and associated street lighting upgrade.
  • Works will be carried out during daylight hours. Some works may be carried out at night where required.
  • There will be some noise disturbance during the work.
  • Temporary lane closures throughout the site can be expected at various stages.
  • Traffic delays will occur throughout the works and we will continue to update you throughout the project.