North West Watermain Renewals - Wayside Ave and Guildford St

Update

What

Replacing the watermains and submains.

Why

The watermains have reached the end of their economic life and increased maintenance costs make replacement more economical.

Where

The entire length of Wayside Avenue and Guildford Street.

When

The Contractor will be establishing on site 7 January 2019 and the works will commence for approximately 12 weeks.

Contact

The contractor is John Fillmore Contracting. Phone 027 522 0270 between 7am to 6pm, Monday to Friday. Advise us if you have specific property access requirements e.g. medical visits, home help, large vehicle deliveries, planned works.

  • There may be times when vehicle access to your property is restricted.
  • This will be temporary and our contractor will door knock beforehand so you can move your vehicle if necessary.