Hoani Street - wastewater renewal

What

Repairs and installing a new lining to wastewater pipes in your street.

Why

The existing pipes have reached the end of their useful life.

Where

Hoani Street, Papanui

When

October 2021 to June 2022. Monday to Friday, 7am to 6pm (weather/site condition dependent).

Contact

The contractor is City Care Ltd. Phone Gareth Maguire on 027 581 932, Monday to Friday, 7am to 6pm. After hours call City Care on 03 941 7200.

Details

  • Most of the pipe renewal on this job will be done using trenchless methodology.   A liner can be installed into the pipe to renew it without digging up the street.  Some pipes will require excavation to carry out localised repairs prior to installing the new liner.
  • The pipes will be cleaned then inspected with CCTV.  Decisions on any pre-repairs are made and repairs done if required.  Then the liner is installed in to the existing pipe through the existing access manholes.
  • Some works my need to be undertaken at night when sewer flows are lower.  Notice will be provided to residents if that is required.
  • Traffic management will be in place to enable the crews to work safely.
  • Wastewater flows from your property will be maintained throughout the works.

Takiuru ki ā mātou ratonga
Log in to our services